Line 28: Line 28:
  
 Electrical components like wires, breakers and other items are separate. Shall be estimated after a measurement and after the design map is made.  Electrical components like wires, breakers and other items are separate. Shall be estimated after a measurement and after the design map is made. 
 +
 +If we have a final of about 100 per watt for the 1 MW system then the system shall generate 5 MWH per day. 
 +
 +1 KWH at Rs 50 x 5000 ( for 5 MWH ) = Rs. 250,000 per day saving. 
 +
 +If Rs 100M are paid and 0.25 M per day are saved then the ROI is 100M/0.25M = 400 days. 
 +
 +This is very good. 
 +
 +If the system is used for 400 days in the day time then the return on estimate is complete. 
 +
 +Life of solar modules is about 30 years or more. 
 +
 +Life of inverters is about 10 to 13 years before maintenance. Maintenance cost is about max 10% of cost. 
 +
 +So over 30 years the inverters shall cost about 1.3x their initial cost. Not much in maintenance. 
 +
 +Make sure inverters are running at max 70 percent capacity for a life of over 10 years without maintenance. 
 +
 +Running an inverter at near 100% capacity in hot climates can cause it to require repairs within 3 years. 
 +
 +Most expensive maintenance cost is cleaning of solar module. 
 +
 +We shall design them to be about 1 meter above the roof so the frame cost is low AND they are easy to clean. 
 +
 +There shall be space between the modules to allow wind movement and further reduce the frame costs while increasing the wind resistance by allowing a passage for it to pass between the adjacent modules. 
 +
 + 
  
  